9600 Compressor Installation, Operation, and Maintenance
P/N 8040540
3-5
C
HELIX  TECHNOLOGY  CORPORATION
-
TI
CRYOGENICS
Figure 3-2: 9600 Compressor Circuit Breaker Terminals (Cover Removed)
NOTE: The phase order in which the conductor terminal lugs are 
connected to circuit breaker terminals X, Y, and Z will be determined 
during the Phase Check Procedure.
NOTE: For installation where one of the three phase legs is at or near 
ground potential, connect that leg to terminal Y on the Compressor as 
shown in Figure 3-2.
10. Install the conductor terminal lugs to the circuit breaker terminals 
X, Y, and Z as shown in Figure 3-2.
11. Torque the screws to 12 in.-lbs (0.14m-kg).
12. Allow enough cable to stay in the electrical enclosure to prevent 
strain on the electrical connections and tighten the screws on the 
cable strain relief.
13. Install the power source end of the power cable according to the 
local electrical codes.
14. Install the circuit breaker terminal cover.
15. Proceed with Phase Check.
(SEE DETAIL A)
REAR PANEL
CIRCUIT BREAKER 
TERMINAL COVER
X
Y
Z
DETAIL A (COVER REMOVED)
THREE PHASE POWER
CRYOPUMP
PHASE
CRYOPUMP MOTOR
PHASE SWITCH