INSTALLATION
Figure 11 - Mounting  Heater  Onto
Mounting  Bracket
Figure 9 - Folding  Anchor
Figure 10 - Popping  Open  Anchor
Wing  For  Thin Walls
Attaching  Mounting  Bracket  to
Wall
Note: 
   Wall    anchors,     mounting
screws,    and    spacers     are     in
hardware  package.  The    hardware
package  is  provided    with  heater.
Attaching  to  Wal l Stud  Method
For  attaching  mounting  bracket to
wall  studs
1.     Drill  holes  at  marked   locations
        using  9/64
"
  drill  bit.
2.     Place   mounting   bracket  onto
         wall. Line up last hole on each
         end of bracket with holes drilled
         in wall.
3.     Insert mounting screws through
        bracket and into wall  studs.
4.     Tighten screws until mounting
        bracket is firmly fastened to
        wall studs.
Attaching  to  Wall  Anchor
Method
For  attaching  mounting  bracket to
hollow  walls  (wall  areas between
studs) or solid  walls (concrete or
masonry)
1.   Drill  holes  at marked  locations
     using   5/16
"
 drill  bit.  For  solid
    walls (concrete or
 
masonry), drill
    at  least 1
"
 deep.
2.   Fold  wall  anchor as  shown in
      Figure 9  below.
3.    Insert  wall  anchor  (wings
       first) into hole. Tap  anchor
       flush  to  wall.
4.    For  thin  walls (1/2
"
  or  less),
       insert  red  key  into  wall
       anchor.  Push  red  key  to
       
"
pop
"
  open  anchor  wings
       (see  Figure 10).
                      IMPORTANT:    Do    not
hammer    key!   For  thick walls
(over  1/2
"
  thick)  or  solid  walls,
do  not  pop  open wings.
5.   Place  mounting  bracket  onto
       wall.  Line  up  last  hole  on
       each end  of  bracket  with wall
       anchors.
6.   Insert  mounting  screws through
      bracket  and  into  wall anchors.
7.   Tighten  screws  until  mounting
      bracket is firmly fastened to wall.
Placing    Heater    on    Mounting
Bracket
1.   Locate  two  horizontal   slots  on
        back    panel    of    heater  (see
      Figure 11).
2.    Place    heater    onto    mounting
     bracket.  Slide  horizontal  slots
        onto      stand-out        tabs        on
      mounting  bracket.
Installing    Bottom    Mounting
Screws
1.   Locate  two  bottom  mounting
      holes. These  holes  are  near
       bottom    on      back     panel   of
        heater(see Figure 12).
2.   Mark    screw   locations   on wall.
3.   Remove   heater    from mounting
      bracket.
4.   If  installing    bottom   mounting
     screws into  hollow  or solid wall,
     install wall anchors.Follow steps
     1  through   4    under    Attaching
     To    Wall    Anchor    Method.   If
     installing   bottom  mounting
     screw
     into   wall   stud,   drill   holes    at
      marked    locations  using   9/64
"
   
  drill  bit.
5.   Replace  heater  onto  mounting
      bracket.
6.   Place  spacers between   bottom
      mounting  holes and  wall  anchor
       or  drilled  holes.
7.   Hold  spacer  in  place   with   one
     hand. With  other  hand,  insert
      mounting         screw         through
     bottom    mounting   hole   and
     spacer.  Place tip  of  screw  in
     opening of wall anchor or drilled
      holes .
8.    Tighten  both  screws  until heater
      is  firmly   secured   to  wall. Do not
       over  tighten.
Note:  Do  not  replace  lower front
       panel  at  this  time. Replace  lower
     front  panel  after  making    gas
     connections  and  checking  for
      leaks (see  pages  9  and  10).
Figure 12 - Installing Bottom
Mounting Screws