 Switching Module Installation 3-5
Installing Modules
Slots 3 through 12—Any switching modules, Network Analysis Module, or RSM
Slots 9 through 12—Layer 3-Fabric Integration Module or ATM-Fabric Integration
Module
Note
The fabric integration modules must be installed in slots 9 through 12 for the
bridging function to work.
Slots 9 through 12—Any LightStream module or Catalyst 8510 campus switch router
(CSR) line module
Slot 13—Reserved for LightStream 1010 ATM switch processor or Catalyst 8510 CSR
switch route processor (SRP) only
Note
If you have LightStream 1010 modules, you can install them in slots 9 through 12.
However, you must install an ATM switch processor in slot 13. If you have Catalyst 8510
CSR line modules, you can install them in slots 9 through 12. However, you must install an
SRP in slot 13.
Install switching-module filler plates, which are blank switching-module carriers, in empty
slots to maintain consistent airflow through the switch chassis.
Caution
To prevent ESD damage, handle switching modules by the carrier edges
only.
Warning
During this procedure, wear grounding wrist straps to avoid ESD
damage to the card. Do not directly touch the backplane with your hand or any
metal tool, or you could shock yourself.