1460 Maintenance Procedures for Avaya Communication Manager 3.0, Media Gateways and Servers
 
Audit and Update Test (#36)
This test sends port level translation data from the switch processor to the DS1 interface circuit 
pack or media module to assure that the trunk’s translation is correct. The port audit operation 
verifies the consistency of the current state of trunk kept in the DS1 interface circuit pack or 
media module and in the switch software.
Table 526: Test #36 Audit and Update Test 
Error 
Code
Test 
Result
Description / Recommendation
ABRT
Internal system error
1018
ABRT
Maintenance is disabled on this trunk.
1. Enable maintenance by entering y in the Maintenance Tests field 
on the change trunk-group form.
2000
ABRT
Response to the test request was not received within the allowable time 
period.
1. Retry the command at 1-minute intervals up to 5 times.
2100
ABRT
Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals up to 5 times.
FAIL
Test failed due to internal system error.
1. Retry the command at 1-minute intervals up to 5 times.
PASS
Trunk translation has been updated successfully. The current trunk states 
kept in the DS1 interface circuit pack or media module and switch software 
are consistent.
If the trunk is busied out, the test will not run, but will return PASS. To verify 
that the trunk is in-service:
1. Enter status-command to verify that the trunk is in-service. If the 
trunk is in-service, no further action is necessary. If the trunk is 
out-of-service, continue to Step 2.
2. Enter release-trunk to put trunk back into in-service.
3. Retry the test command.