Cisco Cisco ONS 15454 M2 Multiservice Transport Platform (MSTP)

Page of 40
Procedure
Step 1
Complete the “NTP-G139 Verify Cisco Transport Planner Reports and Files” task in the chapter “Turn Up a Node” of the
Cisco ONS 15454 DWDM Network Configuration Guide to verify that you have the files and reports prepared by Cisco
Transport Planner for the OADM node.
Step 2
Complete the "DLP-G46 Log into CTC" task in the "
document at the line amplifier
node.
Step 3
Click the Circuits tab.
Step 4
Make a list of the OCHNCs, OCH trails, and OCHCCs that pass through the node on the express path for both the Side
B-to-Side A and Side A-to-Side B directions.
You will delete the optical channel circuits in the next step and use the list to recreate the circuits later. Do not
proceed until you complete the circuit list.
Caution
Step 5
Delete the circuits identified in
Step 4, on page 23
using one or more of the following tasks:
• “DLP-G347 Delete Optical Channel Client Connections” task in the chapter “Create Optical Channel Circuits and
Provisionable Patchcords” of the Cisco ONS 15454 DWDM Network Configuration Guide
• “DLP-G418 Delete an Optical Channel Trail” task in the chapter “Create Optical Channel Circuits and Provisionable
Patchcords” of the Cisco ONS 15454 DWDM Network Configuration Guide
• “DLP-G106 Delete Optical Channel Network Connections” task in the chapter “Create Optical Channel Circuits and
Provisionable Patchcords” of the Cisco ONS 15454 DWDM Network Configuration Guide
Step 6
Click the Provisioning WDM-ANS Internal Patchcords tabs.
Step 7
In the internal patchcords table, click the OPT-PRE COM-TX to OPT-BST COM-RX internal patchcord.
Step 8
Click Delete.
Step 9
On the confirmation dialog, click OK.
Step 10
Remove the physical fiber and attenuators, if present, that connect the COM-TX to COM-RX ports and COM-RX to
COM-TX ports between the OPT-BST and OPT-PRE cards installed in Side B.
Step 11
Click Default Patchcords.
Step 12
Complete the “NTP-G143 Import the Cisco Transport Planner NE Update Configuration File” procedure in the chapter
“Turn Up a Node” of the Cisco ONS 15454 DWDM Network Configuration Guide.
Step 13
Complete the “NTP-G37 Run Automatic Node Setup” task in the chapter “Turn Up a Node” of the Cisco ONS 15454
DWDM Network Configuration Guide
.
Step 14
In node view, click the Circuits tab.
Step 15
Complete one or more of the following procedures to recreate circuits identified in
Step 4, on page 23
that will pass
through the OADM node:
• “DLP-G346 Provision Optical Channel Client Connections” task in the chapter “Create Optical Channel Circuits and
Provisionable Patchcords” of the Cisco ONS 15454 DWDM Network Configuration Guide
• “DLP-G105 Provision Optical Channel Network Connections” task in the chapter “Create Optical Channel Circuits
and Provisionable Patchcords”of the Cisco ONS 15454 DWDM Network Configuration Guide
• “DLP-G395 Create an Optical Channel Trail” task in the chapter “Create Optical Channel Circuits and Provisionable
Patchcords” of the Cisco ONS 15454 DWDM Network Configuration Guide
Cisco recommends that you recreate the circuits one at a
time.
Note
23