Modifications reserved 
Page 50/57 
OPM_LPS_3UO_30K_40K_0US_V010.doc 
Operating Manual LP 33 Series 30 & 40 kVA 
7.2.6 
Complete shutdown of a parallel system 
 
As a result of this procedure the parallel system is completely switched OFF and not powered. 
 
 
NOTE ! 
This procedure involves all equipment powered by parallel system, to be shut down. 
 
 
1.  Perform the command total off on any one of the units. 
 
2.  Switch OFF the output switch Q1 (Pos. 0) on each unit. 
 
3. Remove 
the battery fuses F5, F6, F7 (and eventual external fuses in case of external battery) on 
each unit. 
 
4.  In order to discharge the DC link capacitors, start once more 
the inverter on each unit through the screen
MENU/COMMAND MENU/INVERTER ON
 
 
COMMAND MENU 
INVERTER ON * 
INVERTER OFF 
 
 
Remark: command 
INVERTER ON will be enabled only when 
the inverter voltage of each phase decreases 
below 7 VAC (about 30 seconds). 
 
INVERTER: U1= 
 
7V 
U2=  7V U3=  7V 
Frequency    =    60.0Hz 
Synchronized 
 
Before proceeding to step 5, check on the display panel that 
the DC link voltage (both polarities) Udcp and Udcn has reached 
the minimum voltage of 5 VDC (about 30 seconds). 
 
Udcp=  5V Udcn= 
5V 
Ubp=0V 
Ubn=0V   O 
Charge level  =  0% 
Autonomy = 
0min
 
 
5.  Switch OFF the inverter on each unit entering the screen
MENU/COMMAND MENU/INVERTER OFF 
 
MENU COMANDI 
INVERTER ON 
INVERTER OFF *
 
 
 
6.  Switch OFF the mains power of each unit at the AC input distribution panel. 
 
END OF PROCEDURE 
 
 
 
CAUTION ! 
If the above procedure is not completely performed, it could cause 
serious damages to the UPS. 
 
 
WARNING ! 
In case the procedure described on step “4 - discharge DC link capacitors” cannot 
be completely performed, the DC capacitors could be charged with dangerous 
voltage for about 15 minutes. 
Wait until capacitors are completely discharged before starting the UPS again. 
Apart from the front door, do not open any other part of the UPS