GE LP 33 Manual De Usuario

Descargar
Página de 57
Modifications reserved 
Page 51/57 
OPM_LPS_3UO_30K_40K_0US_V010.doc 
Operating Manual LP 33 Series 30 & 40 kVA 
7.2.7  Restore to normal operation after “total off” 
 
 
NOTE ! 
Make sure the all units of the parallel system to be status of the activation of “total 
off”
, i. e. Q1 closed, Q2 open the battery fuses F5, F6, F7 (and eventual external fuses in 
case of external battery) connected. 
 
 
View of the panel after pressing the button “total off”
• 
All Contactors are open. 
• 
Booster, inverter eand Static-Switch shutdown. 
 
LP 33          40kVA  P1 
APPLICAT. SUPPLY OFF 
= 0% 
 
 
 
 
1. Reset 
total off of the parallel system
Restore the command “total off”,  on any one of the units, by 
entering the screen: MENU/RESET TOTAL OFF 
 
LED TEST 
RESET TOTAL OFF 
* 
 
 
The load is supplied by the mains through the automatic 
bypass

The booster starts automatically. 
 
The LCD screen must display on all Units the status: 
APPLICATION ON BYPASS
 
 
LP 33          40kVA  P1 
APPLICATION ON BYPASS 
= 70% 
 
 
2.  Switch ON the inverter on first unit by entering the screen
MENU/COMMAND MENU/INVERTER ON 
In case of sufficient output power, the output will transfer to 
Inverter. 
 
COMMAND MENU 
INVERTER ON * 
INVERTER OFF 
 
 
3.  Switch ON the inverter on the other units by entering the
screen: MENU/COMMAND MENU/INVERTER ON 
(Do not start the next inverter until the sequence of the previous
one ends – about 10 seconds).
 
 
COMMAND MENU 
INVERTER ON * 
INVERTER OFF 
 
 
LP 33          40kVA  P1 
APPLICATION ON UPS 
= 70% 
 
As soon as the output power of the inverters is sufficient to 
supply the load, the output of the units with running inverter 
will transfer to inverter
The LCD screen must display on all Units the status: 
APPLICATION ON UPS
 
 
 
 
END OF PROCEDURE